Department of Construction

Issuance of Building Permit

Total time (working days) is no more than 10 working days, as follows: a) IPA shall receive application files and check their validity in compliance with the law, transfer them to  Department of...

Issuance of planning certificate and planning information provision

Total time (working day) not exceed 10 days, as follows: a) IPA shall receive application  files and check their validity in compliance with the law and later then transfer them to Department of...

Introduction of construction investment location

Total time (working day) does not exceed 10 days for the locations in detailed construction planning with scale of 1/500 and 1/2000 (hereinafter referred to as planned location); or  20 days for...

Procedures: Survey, information provision and policy approval on investment location

Total time (working day) does not exceed 10 working days. Details are as follows: a) IPA shall receive application dossiers, check their validity in compliance with the law and later transfer them to...

  • Vinh Phuc Province Investment Promotion Information Site

    Department of Planning and Investment of Vinh Phuc province.

    Address: No. 40 Nguyen Trai Street, Dong Da Ward, Vinh Yen City, Vinh Phuc Province.

    Email: investvinhphuc@gmail.com, Phone: (+84).211.3.862.480

    License No. 49/GP-TTĐT, issued on April 13, 2020 by the Department of Information and Communications of Vinh Phuc Province