ODA Capital and State Budget Projects

Appraisal and approval procedures for final settlement of completed projects subject to state fund

Total time shall not exceed 04 months for group A projects, 3.5 months for group B projects, 04 months for group C projects or 03 months for the project required with Construction Economic and...

Appraisal and approval procedures for supplement of construction projects

Total time (working days) does not exceed 37 working days for group A projects; 28 working days for group B projects, 23 working days for group C projects. Details are as follows: a) IPA shall...

Appraisal and approval procedures for supplement of construction time extension

1. Total time (working days) does not exceed: 22 working days for group A projects; 17 working days for group B projects; 15 working days for group C projects. Details are as follows: a) IPA shall...

Appraisal and approval procedures for bidding plan

Total time (working days) does not exceed 20 days with the following details: a) IPA shall receive application files, check their validity in compliance with the law and later transfer them to the...

Appraisal and approval procedures for construction projects

Total time (working days) does not exceed: 37 working days for group A projects, 30 working days for group B projects, 25 working days for group C projects. Details are as follows: a) IPA shall...

  • Vinh Phuc Province Investment Promotion Information Site

    Department of Planning and Investment of Vinh Phuc province.

    Address: No. 40 Nguyen Trai Street, Dong Da Ward, Vinh Yen City, Vinh Phuc Province.

    Email: investvinhphuc@gmail.com, Phone: (+84).211.3.862.480

    License No. 49/GP-TTĐT, issued on April 13, 2020 by the Department of Information and Communications of Vinh Phuc Province