VINH PHUC OBSTETRICS AND PEDIATRICS HOSPITAL
- Location:
In Hop Thinh commune – Tam Duong District, and Dong Van commune – Yen Lac District (or other adequate location upon purpose), close to National Way 2A, 7km away from center of Vinh Yen City.
- Present condition
Land cleared, construction design and cost estimation on item: wall foundation, leveling, approved by the PPC in Decision 1714/QĐ-CT dated June 26th 2015.
- Project goals and scale:
- Project goals: New obstetrics and pediatrics hospital to be built to replace the outdated one with following goals:
- Modernly equipped medication center.
- Providing people, especially mothers and children with healthcare service and protection.
- Overload reduction for national-level hospital, contributing to social-economic development of the local;
- Becoming a satellite hospital of national-level hospitals.
- Scale: Total area: 9.9 ha, serving 500 beds, including:
- Hospitalization technical block: 14 floors, total floor area: 50,547 m2.
- Service building: 5 floors, total floor area: 4,340 m2.
- Department of Nutrition building: 2 floors, total floor area 2,116 m2.
- Department of Infectious building: 3 floors, total floor area 1,689 m2.
- Department of Anti-Infectious building: 2 floors, total floor area 960 m2.
- Department of Pathological Anatomy and Funeral Home: 1 floor, total floor area 680 m2.
- Supporting buildings, infrastructure, internal roads, wastewater treatment system, medical waste treatment system, lighting system, equipment…
- Equipment: modernized and synchronized with buildings according to Vietnam Standards.
- Total estimated capital: about $70 million or upon investment purpose.
- Authorized State Agencies: Vinh Phuc Provincial People’s Committee
- Field of investment: Hospital
- Status: Calling for investment
- Progress:
- 2012: Vinh Phuc Obstetrics and Pediatrics Hospital Project was approved in Decision 2668/QĐ-CT dated October 19th
- From 2013 to 2014: Land clearance, relocation of 110KV electric wire and agriculture discharging channel.
- 2015: Item: Wall foundation, leveling is approved in Decision no 1714/QĐ-CT dated June 24th 2015
- Forms of investments: 100% private capital or upon request.
- Preferred policies:
- Land rents: Free land rents.
- Tax policies:
- Tax exemption for 04 years since the taxable income, a reduction of 50% taxation of the project income for 05 following years, and a preferred enterprise income tax rate of 10% for the rest of its operation.
- Individual income tax: Vietnamese and foreigners working for the Project have their individual income tax reduced by 50%.
- Investors enjoy incentive policies in Law on import tax and export tax for imported equipment using in construction.
- Provincial commitment:
- Procedures: processing by one stop service mechanism; highest priority to support investors during the implementation of the project.
- Implementation process:
- Investors submit Project proposal documentation to Vinh Phuc Investment Promotion Agency for inspection and approval of the PPC;
- Prepare Project profile and apply for the issuance of Certificate of Investment;
- The PPC hands over the investors with clear site;
- The investors now can start the Project.